Can we connect our planned hydro site(s) to the line?

Submitted by patrickboileau on Thu, 09/15/2016 - 13:13
The line will be designed to connect both users and generators of electricity.
 
The Independent Electricity System Operator (IESO) is responsible for issuing power purchase contracts and the Ontario Energy Board’s Transmission System Code sets out the rules for connecting generators to transmission lines. Wataynikaneyap cannot control those processes. However, the proposed line routing passes near several potential hydro generation sites, and having a transmission line in proximity to a planned hydro generation site is a significant step toward making those projects a reality.
 
The IESO is currently restricting new large renewable generation in the Northwest, Northeast, and Sault regions of the province. Feed-in-Tariff Projects (FIT - less than 0.5 MW) are not restricted.